PROJECTS
Zeerust PV Plant 75 MWac
Scope
-
Construction of the RE Capital 2- Substation Control Building
Location
Client
Zeerust/ North West
IstoGuard
Status
Complete -Dec 2020
De Wildt PV Plant 50 MWac
Scope
-
Design/ Construct & Furnish the O&M Building
Location
Client
Brits / North West
IngweGuard
Status
Complete -Dec 2020
Unin 88 kV Distribution Sub. Phase 2
Scope
1. Platform construction.
2. Equipment foundations
3. Structural steel supply/ assemble & install
4. Primary plant equipment installation including stringing
5. Kerbing
6. Procure, supply and install yard stone
Location
Client
Limpopo
Eskom
Status
Complete
Spudshaft 132 KV Distribution Sub.
Scope
-
Refurbish Transformer 6a,6b and 6c bays by constructing 1 x 20MVA 88/6.6kV Transformer bays consist.
-
Refurbish 1 x 88kV line bay and constructing 1 x 88kV line bay.
-
Extend the Earth mat from the newly extended substation side.
-
Install 1 x Transformer bund wall
-
Replace existing fence with new palisade fence.
-
Rotate 1 x 10.5m existing beam by 180° or Construct 1 x 10.5m new beam
-
Construct 6.6kV Twin Bull Busbar (stringing only)
-
Construct 2 x 88kV Bull Busbar (stringing only)
-
Replace 54 x 88KV Long rods including Clamps
-
Install 1x lightning mast
-
Dismantle all primary plant equipment/ cabling and foundations.
-
Procure, supply and install yard stone.
Location
Client
Limpopo
Eskom
Status
Current
Adamskraal 33/132kV Distribution Sub. - Perdekraal Windfarm IPP under (EPC) Contractor
Scope
-
Steel Assembly and Erection.
-
All Secondary Works Including:
-
Earthing of Structural Steel Work and Primary Plant Equipment.
-
Stringing & Clamps.
-
Control & Protection Cabling.
Location
Client
Western Cape
Consolidated Power Projects (CONCO)
Status
Complete
Zeus 400kV Transmission Sub. Feeder 6 and 7
Scope
-
All Secondary Works Including:
-
Stringing Bull Conductor.
-
Control and Protection Cabling.
-
Control Panels Installation & Wiring.
Location
Client
Mpumalanga
ERI - Member of Eskom
Status
Complete
Gopane 132 kV Distribution Sub.
Scope
Bulk Earthworks, Earth Grid, Equipment Foundations, Complete Control Room, Steel Assembly and Erection, Install Primary Plant Equipment, Stringing, Control and Protection Cables, Labelling
Location
Client
Limpopo
Eksom
Status
Complete
Zwartkloof 88kV Distribution Sub.
Scope
-
Construct 66kV busbar Isolator, 66kV transformer breaker, 3x 66kV current transformers and install new 1x 10MVA 66/22kV transformer on the reserved space.
-
Extend the existing 66KV beam and normalize the existing 1x10MVA 66/22kV transformer.
-
Construct fire wall between the transformers.
-
Construct 22kV kiosk breakers for the MV transformers protection.
-
Normalize existing vertical busbar by constructing box type busbar structure.
-
Construct a beam to connect MV side of the transformer to its MV bays.
-
Replace 2x Existing Reclosers by 2 x Kiosk Breakers, 2x Existing Feeder Isolators by 2 x New Knife link Isolators, 1x Existing Transformer 1 22kV Kiosk Breaker by 1 x New Kiosk Breaker.
-
Construct new 22kV feeder bay for new Nqobi feeder.
Location
Client
Bela Bela
Eksom
Status
Complete